[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257546":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1257546,841,1,"单选题","灌注桩的桩顶高程至少要比设计高程高出（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.3～0.5m",false,{"key":16,"text":17,"correct":14},"B","0.5～0.8m",{"key":19,"text":20,"correct":21},"C","0.8～1.0m",true,{"key":23,"text":24,"correct":14},"D","1.0～1.2m","灌注桩的桩位偏差必须符合规范规定，桩顶高程至少要比设计高程高出0.8-1.0m，桩底清孔质量按不同的成桩工艺有不同的要求。每浇筑50m。混凝土必须有一组试件，小于50m3，的桩，每根桩必须有一组试件。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]