[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257534":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1257534,841,1,"单选题","基坑（槽）验槽，应按设计、规范和施工方案等要求进行检查，并做好基坑验槽记录和（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分项工程记录",false,{"key":16,"text":17,"correct":18},"B","隐蔽工程记录",true,{"key":20,"text":21,"correct":14},"C","分部工程记录",{"key":23,"text":24,"correct":14},"D","工序检查记录","基坑或基槽施工结束后再进行后续工作施工时，显然不能再进行复查，因为基坑是隐蔽工程，应进行隐蔽工程检查并填写检查记录。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]