[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257526":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1257526,841,1,"单选题","（ ）宜用于支护结构的支撑形式为角撑、环梁式或边框架式，中间具有较大空间情况下的大型基坑土方开挖。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","放坡挖土",false,{"key":16,"text":17,"correct":18},"B","中心岛式挖土",true,{"key":20,"text":21,"correct":14},"C","盆式挖土",{"key":23,"text":24,"correct":14},"D","逆作法挖土","中心岛式挖土宜用于支护结构的支撑形式为角撑、环梁式或边桁（框）架式，中间具有较大空间情况下的大型基坑土方开挖。此方法可利用中间的土墩作为支点搭设栈桥，挖土机可利用栈桥下到基坑挖土，运土的汽车亦可利用栈桥进入基坑运土，具有挖土和运土的速度快的优点。但由于首先挖去基坑四周的土，支护结构受荷时间长，在软黏土中时间效应显著，有可能增大支护结构的变形量，对于支护结构受力不利。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]