[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257512":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1257512,841,1,"单选题","关于模板拆除的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","底模及其支架拆除应符合设计或规范要求",false,{"key":16,"text":17,"correct":18},"B","后张法预应力构件侧模宜在预应力张拉前拆除",true,{"key":20,"text":21,"correct":14},"C","后张法预应力构件底模宜在预应力张拉前拆除",{"key":23,"text":24,"correct":14},"D","拆模通常先拆承重部分后拆非承重部分","此题不难，对于理论知识扎实、具备一定工程实践经验的考生来说，很简单，主要考核模板拆除的技术要求。相关规范规定：对于后张预应力混凝土结构构件，侧模宜在预应力张拉前拆除；底模支架不应在结构构件建立预应力前拆除。选项A有一定迷惑性，根据相关规范，底模及其支架拆除时，同条件养护试块的抗压强度应符合设计要求；设计无要求时，应符合规范要求。也就是说，—任何底模的拆除既要满足设计规定，又要满足规范要求，而不是符合设计或规范要求。选项D正确说法：拆模通常先拆非承重部分后拆承重部分。故本题正确选项应为“B”。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]