[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257500":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1257500,841,1,"单选题","工程建设概况、工程施工情况、单位工程进度计划、分阶段进度计划、单位工程准备工作计划、劳动力需用量计划，主要材料、设备及加工计划，主要施工机械和机具需用量计划，主要施工方案及流水段划分，各项经济技术指标要求等这些都属于（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工进度计划的分类",false,{"key":16,"text":17,"correct":14},"B","施工进度计划的表达方式",{"key":19,"text":20,"correct":21},"C","单位工程进度计划的内容",true,{"key":23,"text":24,"correct":14},"D","单位工程进度计划的编制依据","单位工程进度计划内容包括：工程建设概况；工程施工情况；单位工程进度计划，分阶段进度计划，单位工程逐步工作计划等。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]