[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257488":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1257488,841,1,"单选题","施工组织设计内容的三要素是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程概况.进度计划.技术经济指标",false,{"key":16,"text":17,"correct":14},"B","施工方案.进度计划.技术经济指标",{"key":19,"text":20,"correct":14},"C","进度计划.施工平面图.技术经济指标",{"key":22,"text":23,"correct":24},"D","施工方案.进度计划.施工平面图",true,"单位工程施工组织设计较完整的内容一般包括：工程概况；施工方案的设计：单位工程施工进度计划；单位工程施工准备工作以及各项资源需要量计划；单位工程施工平面图，质量、安全、降低成本以及季节施工的技术组织保证措施；主要技术经济指标分析。。对于一般常见的建筑结构类型和规模不大的单位工程，施工组织设计可以编制得简单一些，主要内容为：施工方案；施工进度计划；施工平面图，。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]