[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257485":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1257485,841,1,"单选题","单位工程有分包单位施工时，分包工程完成后，应将工程有关资料交（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":14},"B","监理单位",{"key":19,"text":20,"correct":14},"C","设计单位",{"key":22,"text":23,"correct":24},"D","总包单位",true,"工程有总包单位的，应由总包单位负责汇总分包单位提交的资料，没有总包单位的，由建设单位负责分包单位资料的汇总。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]