[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257483":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1257483,841,1,"单选题","应全面负责施工过程的现场管理的人员是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位驻现场代表",false,{"key":16,"text":17,"correct":18},"B","项目经理",true,{"key":20,"text":21,"correct":14},"C","建筑企业总工程师",{"key":23,"text":24,"correct":14},"D","建筑企业法定代表人","项目经理应由法定代表人任命，并根据法定代表人授权的范围、期限和内容，履行管理职责，并对项目实施全过程、全面管理。项目经理不应同时承担两个或两个以上未完项目领导岗位的工作",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]