[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257482":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1257482,841,1,"单选题","标高的竖向传递，宜采用（ ）从首层起始标高线垂直量取。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","钢尺",true,{"key":16,"text":17,"correct":18},"B","水准仪",false,{"key":20,"text":21,"correct":18},"C","经纬仪",{"key":23,"text":24,"correct":18},"D","激光铅直仪","标高的竖向传递，宜采用钢尺从首层起始标高线垂直量取，规模较小的工业建筑或多层民用建筑宜从2处分别向上传递，规模较大的工业建筑或高层建筑宜从3处分别向上传递。施工层抄平之前，应先检测三个传递标高点，当较差小于3mm时，以其平均值作为本层标高基准，否则庄重",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]