[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257474":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1257474,841,1,"单选题","主要建筑物附近的高程控制点，不应少于",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","两个",false,{"key":16,"text":17,"correct":18},"B","三个",true,{"key":20,"text":21,"correct":14},"C","四个",{"key":23,"text":24,"correct":14},"D","五个","建筑物高程控制，应采用水准测量。主要建筑物附近的高程控制点不应少于三个。高程控制点的高程值一般采用工程±o．000高程值。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]