[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257473":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1257473,841,1,"单选题","以下关于施工组织设计的编制原则错误的是",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","符合施工合同或招标文件中有关工程进度.质量.安全.环境保护.造价等方面的要求",false,{"key":16,"text":17,"correct":14},"B","积极开发.使用新技术和新工艺，推广应用新材料和新设备",{"key":19,"text":20,"correct":14},"C","采取技术和管理措施，推广建筑节能和绿色施工",{"key":22,"text":23,"correct":24},"D","坚持科学的施工程序和合理的施工顺序，采用流水施工和网络计划等方法，科学配置资源，合理布置现场，但是不应该采取季节性施工措施",true,"D选择正确的说法是“坚持科学的施工程序和合理的施工顺序，采用流水施工和网络计划等方法，科学配置资源，合理布置现场，采取季节性施工措施，实现均衡施工，达到合理的经济技术指标。”",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]