[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257463":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1257463,841,1,"单选题","高聚物改性沥青防水涂料在防水工程冬期施工环境气温要求中，施工环境气温应达到（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","不低于15℃",false,{"key":16,"text":17,"correct":14},"B","溶剂型不低于5℃，热熔型不低于-10℃",{"key":19,"text":20,"correct":14},"C","不低于0℃",{"key":22,"text":23,"correct":24},"D","热熔剂不低于-10℃",true,"防水工程应依据材料性能确定施工气温界限，最低施工环境气温宜符合教材Puo表2A312061-4的规定，防水材料进场后，应存放于通风、干燥的暖棚内，并严禁接近火源和热源。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]