[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257391":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1257391,841,1,"单选题","工作A有三项紧后工作 B、 C、 D，其持续时间分别为：B=6、C=8、D=7，LFB=14、LFC=16、LFD=14，则LFA为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":14},"B","8",{"key":19,"text":20,"correct":21},"C","7",true,{"key":23,"text":24,"correct":14},"D","3","工作的最迟开始时间＝工作的最迟完成时间一该工作的最早完成时间，B工作的最迟开始时间=14-6=8，C工作的最迟开始时间=16-8=8，D工作的最迟开始时间=14-7=7，A工作的最迟完成时间=min{紧后工作的最迟开始时间}=min{8，8，7}=7。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]