[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257343":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1257343,841,1,"单选题","某工程承包人按规定提前书面通知监理人进行隐蔽工程共同验收，但监理人既未按时到场进行检查，也未按规定及时提出延期要求。在此情况下，下列做法符合《建设工程施工合同（示范文本）》通用条款规定的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包人请示监理人，是否可自行完成隐蔽工程覆盖工作",false,{"key":16,"text":17,"correct":14},"B","监理人需经发包人同意，方可允许承包人自行完成覆盖工作",{"key":19,"text":20,"correct":21},"C","承包人可自行完成隐蔽工程覆盖工作，同时应做好相关记录并报送监理人",true,{"key":23,"text":24,"correct":14},"D","监理人需对已覆盖部位揭开重新检查后，才能签字确认承包人所报送的记录","某工程承包人按规定提前书面通知监理人进行隐蔽工程共同验收，但监理人既未按时到场进行检查，也未按规定及时提出延期要求。在此情况下，下列做法符合《建设工程施工合同（示范文本）》通用条款规定的是承包人可自行完成隐蔽工程覆盖工作，同时应做好相关记录并报送监理人。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]