[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257228":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1257228,841,1,"单选题","某分部分项工程量清单编码为010302006003，则该分部分项工程的清单项目顺序编码是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","01",false,{"key":16,"text":17,"correct":14},"B","02",{"key":19,"text":20,"correct":14},"C","006",{"key":22,"text":23,"correct":24},"D","003",true,"例如某房屋建筑与装饰工程一个标段（或合同段）的工程量清单中含有三个单位工程，每一-单位工程中都有项目特征相同的实心砖墙，在工程量清单中又需反映三个不同单位工程的实心砖墙工程量时，则第--个单位工程的实心砖墙的项目编码应为010401003001,第二个单位工程的实心砖墙的项目编码应为010401003002，第三个单位工程的实心砖墙的项目编码应为010401003003，并分别列出各单位工程实心砖墙的工程量。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]