[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257205":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1257205,841,1,"单选题","已知某挖土机挖土，一次正常循环工作时间是40秒，每次循环平均挖土量0.3m3，机械正常利用系数为0.8，机械幅度差为25%。则该机械挖土方1000m3的预算定额机械耗用台班量是（ ）台班。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","4.63",false,{"key":16,"text":17,"correct":14},"B","5.79",{"key":19,"text":20,"correct":21},"C","7.23",true,{"key":23,"text":24,"correct":14},"D","7.41","本题考查的是预算定额及其基价编制。机械台班的产量定额＝8×纯工作1h正常生产率×机械的时间利用系数＝8×纯工作1h正常循环次数×一次循环生产的产品数量×机械的时间利用系数＝8×（60×60\u002F40）×0.3×0.8＝172.8（m3\u002F台班）。时间定额＝1\u002F172.8（台班\u002Fm3）。预算定额机械台班消耗量=施工定额机械台班定额×（1＋机械幅度差系数）＝1000×1\u002F172.8×（1＋25％）＝7.23（台班\u002F1000m3）。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]