[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257201":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1257201,841,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》GB50854，关于基础土方开挖的工程量计算，说法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","基础设计底面积乘以基础埋深",false,{"key":16,"text":17,"correct":14},"B","基础设计底面积乘以基础设计高度",{"key":19,"text":20,"correct":21},"C","基础垫层设计底面积乘以挖土深度",true,{"key":23,"text":24,"correct":14},"D","基础垫层设计底面积乘以基础设计高度和垫层厚度之和","根据《房屋建筑与装饰工程工程量计算规范》GB50854，关于基础土方开挖的工程量计算，说法正确的是基础垫层设计底面积乘以挖土深度",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]