[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257199":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1257199,841,1,"单选题","建筑安装工程直接费由直接工程费和（ ）组成。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","间接费",false,{"key":16,"text":17,"correct":14},"B","利润",{"key":19,"text":20,"correct":21},"C","措施费",true,{"key":23,"text":24,"correct":14},"D","税金","建筑安装工程直接费由直接工程费和措施费组成。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]