[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257181":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1257181,841,1,"单选题","沉降观测时一般是先后视水准基点，接着依次前视各沉降观测点，最后再后视水准基点。两次后视读数之差不应超过（ ）mm。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","±0.5",false,{"key":16,"text":17,"correct":18},"B","±1",true,{"key":20,"text":21,"correct":14},"C","±2",{"key":23,"text":24,"correct":14},"D","±3","沉降观测时一般是先后视水准基点，接着依次前视各沉降观测点，最后再后视水准基点。两次后视读数之差不应超过±1mm。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]