[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1257177":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1257177,841,1,"单选题","施工层抄平前应先检查标高引测各点高程误差，当相互间误差小于（ ）mm时，以其各点的平均值作为本层标高引测点。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":18},"B","3",true,{"key":20,"text":21,"correct":14},"C","5",{"key":23,"text":24,"correct":14},"D","10","施工层抄平前应先检查标高引测各点高程误差，当相互间误差小于3mm时，以其各点的平均值作为本层标高引测点。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)基础知识","建筑工程",0]