[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256790":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256790,840,3,"判断题","水泥混凝土道路在面层混凝土弯拉强度达到设计强度的80%前，不得开放交通。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"2.城镇道路工程施工开放交通的规定热拌沥青混合料路面应待摊铺层自然降温至表面温度低于50C后，方可开放交通。水泥混凝土道路在面层混凝土弯拉强度达到设计强度，且填缝完成前，不得开放交通。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]