[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256771":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256771,840,3,"判断题","采用工程量清单计价方式，投标单位对自身发生的成本和单价负责，同时也对工程量的变更来承担风险。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"投标单位对自身发生的成本和单价等负责，但是由于工程量的变更或工程量清单编制过程中的计算错误等则由建设单位承担风险。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]