[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256769":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256769,840,3,"判断题","施工项目成本控制的第一步是进行成本预测。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"施工项目成本管理的第一步是进行成本预测。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]