[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256765":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256765,840,3,"判断题","根据《市政工程工程量计算规范》（GB50857-2013），管道铺设中，钢管的工程量计算是按设计图示中心线长度以延长米计算，并扣除附属构筑物、管件及阀门等所占长度。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"根据《市政工程工程量计算规范》（GB50857-2013），管道铺设中，钢管的工程量计算是按设计图示中心线长度以延长米计算，不扣除附属构筑物、管件及阀门等所占长度。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]