[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256754":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256754,840,3,"判断题","对市政工程进行工程量计算时，应结合选定的施工方法计算，不需考虑安全技术、质量保证等因素。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"对市政工程进行工程量计算时，应结合选定的施工方法计算，需考虑安全技术、质量保证等因素。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]