[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256668":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256668,840,3,"判断题","事前控制的目标是确保工序质量合格，关键是坚持质量标准，重点是工序质量、工作质量和质量控制点的控制。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"事前质量控制：对于市政工程项目事前质量控制所对应的是施工准备阶段的质量控制，施工准备阶段的质量控制是指项目正式施工活动开始前，对项目施工各项准备工作及影响项目质量的各因素和有关方面进行的质量控制。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]