[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256662":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256662,840,3,"判断题","施工组织的基本方式有三种：等节拍、不等节拍、无节奏流水施工。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"按流水施工节奏特征分类，流水施工可以分为有节拍流水施工和元节拍流水施工。有节拍流水施工又分为等节拍流水施工和异节拍流水施工。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]