[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256661":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256661,840,3,"判断题","对于大型工程项目，在编制控制性施工进度计划时，工作项目应尽可能划分的细一些，可划分到分项工作。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"对于大型工程项目，经常需要编制控制性施工进度计划，此时工作项目可划分的粗一些，一般只明确到分部工程。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]