[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256658":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256658,840,3,"判断题","在双代号时标网络计划中，用虚箭线表小虚工作，用波形线表示总时差。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"时标网络计划应以实箭线表示工作，以虚箭线表示虚工作，以波形线表示工作的自由时差和间隔时间（虚工作中的自由时差）。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]