[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256657":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256657,840,3,"判断题","在编制施工进度计划时，有时需要划分施工段，其目的是为了适应顺序作业施工的需要。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"划分施工段的目的：①多创造工作面为下道工序尽早开工创造条件；②不同的工序（不同工种的专业施工队）在不同的工作面上平行作业。只有划分施工段，才能展开流水作业。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]