[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256651":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256651,840,3,"判断题","当施工方案确定之后，工作项目之间的组织工关系也即随之确定。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"当施工方案确定之后，工作项目之间的工艺关系也就随之确定。如果违背这种关系，将不可能施工或者导致工程质量事故和安全事故的出现，或者造成返工浪费。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]