[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256650":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256650,840,3,"判断题","在安排某桥梁工程施工顺序时，按照工艺关系必须要先完成下部结构施工，才能安排上部梁的预制和安装工作。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"按照工艺关系不一定要先完成下部结构施工，才能安排上部梁的预制和安装工作。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]