[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256649":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256649,840,3,"判断题","对于大型工程项目，在编制控制性施工进度计划时，工作项目的划分应细些。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"参与工程建设的每一个单位均要编制和自己任务相适应的进度计划。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]