[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256648":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256648,840,3,"判断题","某城市道路改建工程，项目经理部在开工初期编制了施工总进度计划和年度计划图，用以指导现场施工，这种做法是正确的。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"编制施工总进度计划的基本要求是：保证工程施工在合同规定的期限内完成；迅速发挥投资效益；保证施工的连续性和均衡性；节约费用、实现成本目标。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]