[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256644":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256644,840,3,"判断题","在编制某市政道路工程施工进度计划时，拟采用流水作业法，划分施工段时应注意各施工段；各施工段上所消耗的材料用量尽可能相近。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"流水作业法是将报建工程项目划分若干施工段和工序根据工艺要求组织多个专业队伍，相隔定的时间，按施工顺序依次投人各个施工段进行施工，完成各自的施工任务。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]