[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256642":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256642,840,3,"判断题","承包单位的进度控制报告应提交给业主，作为其控制进度、核发进度款的依据。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"承包单位的进度控制报告应提交给监理工程师，千字为其控制进度、核发进度款的依据。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]