[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256640":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256640,840,3,"判断题","主要材料需要量计划，是备料和确定仓库、堆场面积的依据，但对组织材料运输没有太大作用。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"主要材料需要计划，是备料、供料和确定仓库、堆场面积及组织运输的依据，其编制方法是将施工计划表中各施工过程的工程量按材斜规格，数量，使用时间计算汇总而得。对于某些部分分项工程是有多种材料组成应按各种材料分类算。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]