[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256638":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256638,840,3,"判断题","当施工项目的进度计划用时标网络计划表达时，可采用s形曲线比较法进行实际进度与计划进度的比较。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"一般情况下，进度控制人员在计划实施前绘制出计划S形曲线，在项目实施过程中，按规定时间将检查的实际完成任务情况与计划S形曲线绘制在同一张图上。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]