[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256636":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256636,840,3,"判断题","劳动量和机械台班数据应当根据各个部分分项工程的工程量、施工方法和现场的概算定额，并结合当地不发地的具体情况加以确定。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"劳动量和机械台班量是根据各施工项目的工程量、施工方法和现行的施工定额，并结合当时当地的具体情况加以确定。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]