[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256633":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256633,840,3,"判断题","网络计划中任何工作实际进度比计划进度落后都将影响总工期，需采取措施进行调整。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"若工作尚有总时差小于原有总时差，但仍为正值则说明该工作的实际进度比计划进度拖后，产生的偏差值为二者之差，但不影响总工期。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]