[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256631":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256631,840,3,"判断题","在双代号网络图中，当计划工期与计算工期相等时，自由时差为零的工作为关键工作。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"网络图中线路持续时间最长的线路称为关键路线，位于关键线路上的工作称为关键工作，关键工作具备的特点是自由时差为零、总时差最小。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]