[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256630":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256630,840,3,"判断题","在编制施工进度计划的初始方案时，尽可能组织顺序作业，力求资源需要量最",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"按照工艺的合理性和工序问尽量穿插，搭接和平行作业方法，将各施工阶段（分部工程）的流水作业图表最大限度地搭接起来，即得单位工程施工进度计划的初始方案。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]