[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256621":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1256621,840,3,"判断题","编制市政工程单位工程施工进度计划时，需要依据施工承包合同、施工组织设计、承包人的管理水平和设备状况，但与工程所有地的施工条件无关。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"需要依据施工承包合同、施工组织设计、承包人的管理水平和设备状况，工程所有地的施工条件等。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)专业管理实务 岗位知识","建筑工程",0]