[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256599":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1256599,840,2,"多选题","施工项目成本分析，就是根据（ ）提供的资料，对施工成本的形成过程和影响成本的因素进行分析，以寻求进一步降低成本的途径。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","事中控制",false,{"key":16,"text":17,"correct":14},"B","事后控制",{"key":19,"text":20,"correct":21},"C","业务核算",true,{"key":23,"text":24,"correct":21},"D","会计核算",{"key":26,"text":27,"correct":21},"E","统计核算","CDE","施工项目成本分析，就是根据业务核算、会计核算、统计核算提供的资料，对施工成本的形成过程和影响成本的因素进行分析，以寻求进一步降低成本的途径。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)专业管理实务 岗位知识","建筑工程",0]