[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256596":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1256596,840,2,"多选题","按项目施工的进展进行成本分析的内容包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","年度成本分析",true,{"key":16,"text":17,"correct":14},"B","月（季）度成本分析",{"key":19,"text":20,"correct":21},"C","成本盈亏异常分析",false,{"key":23,"text":24,"correct":21},"D","机械使用费分析",{"key":26,"text":27,"correct":14},"E","分部分项工程成本分析","ABE","按项目施工的进展进行成本分析的内容包括年度成本分析、月（季）度成本分析、分部分项工程成本分析。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)专业管理实务 岗位知识","建筑工程",0]