[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256595":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1256595,840,2,"多选题","施工项目成本是指工程项目的施工过程中所发生的全部生产费用的总和，主要由（ ）构成。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","直接成本",true,{"key":16,"text":17,"correct":14},"B","间接成本",{"key":19,"text":20,"correct":21},"C","计划成本",false,{"key":23,"text":24,"correct":21},"D","管理成本",{"key":26,"text":27,"correct":14},"E","税金","ABE","施工项目成本是指在工程项目的施工过程中所发生的全部生产费用的总和，主要由直接成本、间接成本和税金构成，其中间接成本和税金分配取决于企业与项目部具体约定。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)专业管理实务 岗位知识","建筑工程",0]