[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256589":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1256589,840,2,"多选题","A公司中标的某城市场高架跨线桥工程，为15跨25m预应力简支梁桥，桥面宽22m，采用?1200mm的钻孔灌注桩基础，埋置式承台，Y型独立式立柱。工程中标价2850万元。经过成本预测分析，项目目标成本为2600万，其中间接成本占10％。在工程进行过程中发生了如下事件：事件1.工程开工2个月后，因资金不足，贷款500万元，共支付利息30万元。事件2.某承台开挖时发现文物，按上级有关部门要求停工30d，导致总工期拖延10d，未发生直接成本损失。 项目部编制目标成本计划的依据有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","合同文件",true,{"key":16,"text":17,"correct":14},"B","施工组织设计",{"key":19,"text":20,"correct":14},"C","设计图纸",{"key":22,"text":23,"correct":14},"D","投标报价清单",{"key":25,"text":26,"correct":27},"E","预算定额",false,"ABCD","项目部编制目标成本计划的依据有合同文件、施工组织设计、设计图纸、投标报价清单。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)专业管理实务 岗位知识","建筑工程",0]