[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256588":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1256588,840,2,"多选题","根据《市政工程工程量计算规范》（GB508572013），强夯法加固地基列清单工程量时需要根据（ ）项目特征分别列项。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","夯击能量",true,{"key":16,"text":17,"correct":14},"B","夯击遍数",{"key":19,"text":20,"correct":14},"C","地耐力要求",{"key":22,"text":23,"correct":24},"D","夯击影响深度",false,{"key":26,"text":27,"correct":14},"E","夯填材料种类","ABCE","根据《市政工程工程量计算规范》（GB508572013），强夯法加固地基列清单工程量时需要根据夯击能量、夯击遍数、地耐力要求、夯填材料种类项目特征分别列项。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)专业管理实务 岗位知识","建筑工程",0]