[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256572":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1256572,840,2,"多选题","桩基工程专项施工方案应由施工项目部技术负责人向项目部（ ）交底。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","技术管理人员",true,{"key":16,"text":17,"correct":14},"B","质量管理人员",{"key":19,"text":20,"correct":21},"C","班组长",false,{"key":23,"text":24,"correct":21},"D","设备管理人员",{"key":26,"text":27,"correct":14},"E","安全管理人员","ABE","桩基工程专项施工方案应由施工项目部技术负责人向项目部技术管理人员、质量管理人员、安全管理人员交底。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)专业管理实务 岗位知识","建筑工程",0]