[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256547":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1256547,840,2,"多选题","在编制完成单位工程施工进度计划时，需要编制的资源需要量计划主要有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","劳动力需要计划",true,{"key":16,"text":17,"correct":14},"B","主要材料需要计划",{"key":19,"text":20,"correct":21},"C","临时材料需要计划",false,{"key":23,"text":24,"correct":14},"D","构件和半成品需要量计划",{"key":26,"text":27,"correct":14},"E","施工机械需要量计划","ABDE","编制完成单位工程施工进度计划时，需要编制的资源需要量计划主要有劳动力需要计划、主要材料需要计划、构件和半成品需要量计划。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)专业管理实务 岗位知识","建筑工程",0]